Contracts awarded
$18.1b
8 contracts awarded by Sydney Metro.
Published budget: $27 billion to $29 billion to complete, NSW Government estimate, December 2025
Sydney Metro West is a new 24-kilometre underground metro railway between Westmead and the Sydney CBD. Gamuda is designing and building five of its nine stations for Sydney Metro under the Stations Package West contract.
Westmead, SydneyWestern Sydney
Contracts awarded
$18.1b
8 contracts awarded by Sydney Metro.
Published budget: $27 billion to $29 billion to complete, NSW Government estimate, December 2025
Builder
Gamuda
Principal contractor, Stations Package West
Government client
Sydney Metro
Status
On now
Next step: 2026
$18.1b across 8 contracts, awarded by Sydney Metro
Trains, Systems, Maintenance and Operations
Metro Trains West Consortium, a joint venture led by MTR Corporation with CRRC Corporation Limited, awarded December 2025
$3.96b
$3.96 billion, NSW Government, January 2026. Signed in December 2025. Source
Linewide Package
John Holland, awarded December 2025
$3.2b
$3.2 billion, NSW Government, January 2026. Signed in December 2025. Source
Stations Package West
Gamuda, awarded December 2025
$2.85b
$2.85 billion, NSW Government, January 2026. Signed in December 2025. Source
Western Tunnelling Package
Gamuda Australia and Laing O'Rourke Consortium, awarded March 2022
$2.16b
$2.16 billion, Sydney Metro, March 2022. Value at award. Source
Central Tunnelling Package
Acciona Construction Australia and Ferrovial Construction (Australia) Joint Venture, awarded July 2021
$1.96b
$1.96 billion, Sydney Metro, July 2021. Value at award. Source
Eastern Tunnelling Package
John Holland, CPB Contractors, and Ghella joint venture, awarded November 2022
$1.63b
$1.63 billion, Sydney Metro, November 2022. Value at award. Source
Hunter Street Station and Precinct, Precinct Development Partner
Lendlease, Mirvac, and Coombes Property Group, awarded December 2025
$1.5b
$1.5 billion, NSW Government, January 2026. Signed in December 2025. Source
Parramatta Metro station and integrated station development
Gamuda Engineering, Gamuda, and MTR Corporation, awarded September 2026
$880m
$880 million, NSW Government, September 2026. Source
Tunnelling finished in March 2026. The line will double rail capacity between Parramatta and the Sydney CBD and has a target opening date of 2032.
Westmead metro station site, Hawkesbury Road, Westmead, Western Sydney
Gamuda lists Stations Package West work packages on Gateway by ICN. Create a company profile there and register interest in the packages that suit you. Gamuda asks suppliers to contact ICN first to understand the expression of interest process.
Sydney Metro West Stations Package West on Gateway by ICNNSW Aboriginal Procurement Policy applies. How APP works
Bring along suppliers you already use if they are not already on the Birak Marketplace. There are no onboarding fees and generally most suppliers can have an e-store on the Birak Marketplace.
Keep the suppliers you already use. We set each one up as a store on Birak, so your Indigenous spend and your procurement sit in one place.
BRK-TZW7KR and its compliance documents.Optional: one trade account puts every store on credit. Apply for 30-day credit terms
Answered from the sources below, as checked on 11 November 2026.
CurrentTransport
St Marys, Sydney
Parklife Metro
Station fit-out under way
UpcomingTransport
Melrose Park, Sydney
John Holland
Enabling works under way, main works in procurement

CurrentTransport
Woolloongabba, Brisbane
Pulse consortium
Station fit-out and testing