CurrentEnergyEarly construction

Marinus Link Stage 1

Marinus Link Stage 1 is a 750 megawatt electricity and data interconnector between North West Tasmania and Victoria's Latrobe Valley. The client is Marinus Link Pty Ltd, which the Australian, Victorian, and Tasmanian governments own together, with the Australian Government holding 49 per cent.

Heybridge, BurnieNorth West Tasmania

Contracts awarded

$994m

1 contract awarded by MLPL.

Published budget: $3.47 billion in 2023 dollars, the Australian Energy Regulator's February 2026 decision on Stage 1 construction costs

Builder

TasVic Greenlink

DT Infrastructure and Samsung C&T

Balance of works contract: converter station construction at Heybridge and Hazelwood, equipment installation, and land cable civil works

Government client

MLPL

Marinus Link Pty Ltd

Status

On now

Next step: 2030

Contracts awarded

$994m in 1 contract, awarded by MLPL

  1. Balance of works: converter station construction, equipment installation, and land cable civil works

    TasVic Greenlink (DT Infrastructure and Samsung C&T Corporation), awarded December 2025

    $994m

    $994 million in nominal dollars, Marinus Link Pty Ltd, December 2025. Source

Timeline

  1. 1 August 2025Final investment decisionDone
  2. 3 September 2025Financial closeDone
  3. 17 December 2025Civil and construction contract signedDone
  4. 2 October 2026Sod turning ceremonyDone
  5. 13 October 2026Heybridge planning permit affirmedDone
  6. By 2030Stage 1 completionNext

What is being built

TasVic Greenlink, a joint venture of DT Infrastructure and Samsung C&T, holds the $994 million contract to build the converter stations at Heybridge, near Burnie, and at Hazelwood. Hitachi Energy supplies the converter technology, and Prysmian makes and lays the cables.

  • Heybridge converter station near Burnie, on the site of a former tioxide factory
  • Hazelwood converter station in the Latrobe Valley
  • Converter hall, control and auxiliaries building, and structural steelwork at Heybridge
  • Bulk earthworks, site access and internal roads, drainage, and foundations at Heybridge
  • Four transformers and 24 valve structures at each converter station
  • Security fencing, firefighting systems, and a fire water tank at Heybridge
Show all 10
  • 255 km of undersea cable across Bass Strait
  • 90 km of underground cable in Gippsland, in conduits laid by open trenching and horizontal directional drilling
  • Shore crossings at Heybridge and Waratah Bay by horizontal directional drilling
  • Fibre optic terminal station at Sandy Point

Where it is

Heybridge converter station site, corner of Bass Highway and Minna Road, Heybridge, North West Tasmania

Barlow Park Stadium upgradeMoreton Bay Indoor Sports CentreQueensland Academy for Health Sciences, RockhamptonCooktown Multipurpose Health Service redevelopmentPCYC PimpamaTownsville Correctional Centre Capacity UpliftNew Toowoomba HospitalIpswich Hospital Expansion Stage 2Logan Hospital Expansion Stage 2Corymbia Reserve State High School and Ridgeview Special SchoolNorth Queensland StadiumLockyer Valley Correctional CentreCairns Convention Centre Expansion and RefurbishmentRoma Hospital RedevelopmentFortitude Valley State Secondary CollegeBrisbane StadiumNational Aquatic CentreCross River RailSydney Metro WestSydney Metro Western Sydney AirportWestern Harbour TunnelParramatta Light Rail Stage 2Suburban Rail Loop EastNorth East LinkMelbourne Airport RailSubmarine Rotational Force West Priority Works, HMAS StirlingHenderson Defence PrecinctRAAF Base Tindal Redevelopment Stage 6 and airfield worksOsborne Submarine Construction YardSnowy 2.0Inland RailNewcastle to Sydney High Speed RailMarinus Link Stage 1Australian War Memorial Development ProjectTorrens to Darlington (T2D)Anna Meares Velodrome upgradeBrisbane Aquatic Centre upgradeBrisbane International Shooting Centre upgradeBrisbane SX International BMX Centre upgradeChandler Sports Precinct upgradeLogan Indoor Sports CentrePara Sport FacilityQueensland Tennis Centre upgradeRedland Whitewater CentreRockhampton Flatwater FacilitySunshine Coast Mountain Bike CentreSunshine Coast Stadium upgradeToowoomba Showgrounds upgrade
UpcomingCurrentCompleted

Supplying this project

Targets published for this project

  • 15%of works delivered by trainees, apprentices, cadets and/or upskilling workers, a Marinus Link target
  • 2%First Nations employment, in TasVic Greenlink's draft targets
  • 50%local employment in Tasmania, in TasVic Greenlink's draft targets
  • 10%local employment in Victoria, in TasVic Greenlink's draft targets
  • 20%local business expenditure, in TasVic Greenlink's draft targets
  • 10%local labour upskilling, in TasVic Greenlink's draft targets

How to get in

Each lead contractor publishes its open works packages on its ICN Gateway page. To send TasVic Greenlink an expression of interest, a company needs an ICN Gateway company profile.

TasVic Greenlink's ICN Gateway page

The rules

Australian Industry Participation Plan, approved under the Australian Jobs Act 2013 applies. How IPP works

Your supply chain brought to Birak

Bring along suppliers you already use if they are not already on the Birak Marketplace. There are no onboarding fees and generally most suppliers can have an e-store on the Birak Marketplace.

Bring your own suppliers

Your supply chain, as stores on Birak

Keep the suppliers you already use. We set each one up as a store on Birak, so your Indigenous spend and your procurement sit in one place.

  1. 1Send us your suppliersList them, with a contact at each.
  2. 2We set up their storesEach one goes on Birak with the products you buy from it.
  3. 4Order as you do nowEvery order carries BRK-AXF423 and its compliance documents.

Optional: one trade account puts every store on credit. Apply for 30-day credit terms

Common questions

Answered from the sources below, as checked on 11 November 2026.

Who is building Marinus Link Stage 1?
TasVic Greenlink: DT Infrastructure and Samsung C&T. Balance of works contract: converter station construction at Heybridge and Hazelwood, equipment installation, and land cable civil works.
What contracts have been awarded for Marinus Link Stage 1, and what are they worth?
Balance of works: converter station construction, equipment installation, and land cable civil works, TasVic Greenlink (DT Infrastructure and Samsung C&T Corporation): $994 million in nominal dollars, Marinus Link Pty Ltd, December 2025.
What is the budget for Marinus Link Stage 1?
$3.47 billion in 2023 dollars, the Australian Energy Regulator's February 2026 decision on Stage 1 construction costs.
What is the timeline for Marinus Link Stage 1?
Final investment decision: 1 August 2025. Financial close: 3 September 2025. Civil and construction contract signed: 17 December 2025. Sod turning ceremony: 2 October 2026. Heybridge planning permit affirmed: 13 October 2026. Stage 1 completion: By 2030.
What are the local and Indigenous participation targets on Marinus Link Stage 1?
15% of works delivered by trainees, apprentices, cadets and/or upskilling workers, a Marinus Link target. 2% First Nations employment, in TasVic Greenlink's draft targets. 50% local employment in Tasmania, in TasVic Greenlink's draft targets. 10% local employment in Victoria, in TasVic Greenlink's draft targets. 20% local business expenditure, in TasVic Greenlink's draft targets. 10% local labour upskilling, in TasVic Greenlink's draft targets.
How do suppliers and subcontractors get work on Marinus Link Stage 1?
Each lead contractor publishes its open works packages on its ICN Gateway page. To send TasVic Greenlink an expression of interest, a company needs an ICN Gateway company profile.
  • CurrentEnergy

    Snowy 2.0

    Lobs Hole, Tumut

    Future Generation Joint Venture

    Tunnelling under way

Supplying this job?

Send your plans or a list. The Project ID goes with your quote, so we match it to the job.

CallGet a quote

Set your delivery site

We deliver Australia-wide. Your site goes with your quote request, and freight is quoted with your order.