UpcomingTransportEnabling works under way, main works in procurement

Parramatta Light Rail Stage 2

Parramatta Light Rail Stage 2 will extend light rail from the Parramatta CBD to Sydney Olympic Park, with 14 stops over 10 kilometres of new track. John Holland is building the Enabling Works for Transport for NSW, including a 320-metre bridge over the Parramatta River between Melrose Park and Wentworth Point.

Melrose Park, SydneyWestern Sydney

Contracts awarded

$322m

1 contract awarded by TfNSW.

Published budget: $3 billion in funding to date, NSW Government, January 2026

Builder

John Holland

Enabling Works contract, the first 1.3 kilometres of alignment and the Parramatta River bridge

Government client

TfNSW

Transport for NSW

Status

Upcoming

Next step: 2027

Contracts awarded

$322m in 1 contract, awarded by TfNSW

  1. Enabling Works

    John Holland Pty Ltd, awarded September 2024

    $322m

    $322 million, NSW Government, September 2024. Source

Timeline

  1. 19 September 2024Enabling Works contract awardedDone
  2. October 2025Enabling works construction startsDone
  3. 30 January 2026Main works approved and procurement announcedDone
  4. October 2026First bridge deck segment pouredDone
  5. Early 2027Main works construction startsNext
  6. Early 2028Bridge construction completesLater

What is being built

The Stage 2a main works contract, from Camellia to Wentworth Point, is in procurement. The NSW Government says main works construction will begin in early 2027.

  • 10 kilometres of new two-way light rail track with 14 stops
  • Enabling Works: the first 1.3 kilometres of new light rail alignment
  • 320-metre public and active transport bridge over the Parramatta River between Melrose Park and Wentworth Point
  • Upgrades to nearby public spaces, including Archer Park
  • Stage 2a: 4.5 kilometres of new dual track and nine stops from Camellia to Wentworth Point
  • New public and active transport bridge linking Camellia and Rydalmere
Show all 10
  • Expanded stabling and maintenance facility
  • Additional light rail vehicles
  • 9.5 kilometres of walking and cycling links, including 8.5 kilometres of new shared paths
  • Shared light rail and pedestrian zone in Sydney Olympic Park

Where it is

Parramatta River bridge site, between Melrose Park and Wentworth Point, Western Sydney

Barlow Park Stadium upgradeMoreton Bay Indoor Sports CentreQueensland Academy for Health Sciences, RockhamptonCooktown Multipurpose Health Service redevelopmentPCYC PimpamaTownsville Correctional Centre Capacity UpliftNew Toowoomba HospitalIpswich Hospital Expansion Stage 2Logan Hospital Expansion Stage 2Corymbia Reserve State High School and Ridgeview Special SchoolNorth Queensland StadiumLockyer Valley Correctional CentreCairns Convention Centre Expansion and RefurbishmentRoma Hospital RedevelopmentFortitude Valley State Secondary CollegeBrisbane StadiumNational Aquatic CentreCross River RailSydney Metro WestSydney Metro Western Sydney AirportWestern Harbour TunnelParramatta Light Rail Stage 2Suburban Rail Loop EastNorth East LinkMelbourne Airport RailSubmarine Rotational Force West Priority Works, HMAS StirlingHenderson Defence PrecinctRAAF Base Tindal Redevelopment Stage 6 and airfield worksOsborne Submarine Construction YardSnowy 2.0Inland RailNewcastle to Sydney High Speed RailMarinus Link Stage 1Australian War Memorial Development ProjectTorrens to Darlington (T2D)Anna Meares Velodrome upgradeBrisbane Aquatic Centre upgradeBrisbane International Shooting Centre upgradeBrisbane SX International BMX Centre upgradeChandler Sports Precinct upgradeLogan Indoor Sports CentrePara Sport FacilityQueensland Tennis Centre upgradeRedland Whitewater CentreRockhampton Flatwater FacilitySunshine Coast Mountain Bike CentreSunshine Coast Stadium upgradeToowoomba Showgrounds upgrade
UpcomingCurrentCompleted

Supplying this project

How to get in

John Holland lists Enabling Works work packages on Gateway by ICN. Create a company profile there and register interest in open packages. Tenders are scored 80% on price and 20% on non-financial criteria, including sustainability.

Parramatta Light Rail Stage 2 Enabling Works on Gateway by ICN

The rules

NSW Aboriginal Procurement Policy (APP) applies. How APP works

No targets published yet. The tender documents set them.

Your supply chain brought to Birak

Bring along suppliers you already use if they are not already on the Birak Marketplace. There are no onboarding fees and generally most suppliers can have an e-store on the Birak Marketplace.

Bring your own suppliers

Your supply chain, as stores on Birak

Keep the suppliers you already use. We set each one up as a store on Birak, so your Indigenous spend and your procurement sit in one place.

  1. 1Send us your suppliersList them, with a contact at each.
  2. 2We set up their storesEach one goes on Birak with the products you buy from it.
  3. 4Order as you do nowEvery order carries BRK-N6NP43 and its compliance documents.

Optional: one trade account puts every store on credit. Apply for 30-day credit terms

Common questions

Answered from the sources below, as checked on 11 November 2026.

Who is building Parramatta Light Rail Stage 2?
John Holland. Enabling Works contract, the first 1.3 kilometres of alignment and the Parramatta River bridge.
What contracts have been awarded for Parramatta Light Rail Stage 2, and what are they worth?
Enabling Works, John Holland Pty Ltd: $322 million, NSW Government, September 2024.
What is the budget for Parramatta Light Rail Stage 2?
$3 billion in funding to date, NSW Government, January 2026.
What is the timeline for Parramatta Light Rail Stage 2?
Enabling Works contract awarded: 19 September 2024. Enabling works construction starts: October 2025. Main works approved and procurement announced: 30 January 2026. First bridge deck segment poured: October 2026. Main works construction starts: Early 2027. Bridge construction completes: Early 2028.
How do suppliers and subcontractors get work on Parramatta Light Rail Stage 2?
John Holland lists Enabling Works work packages on Gateway by ICN. Create a company profile there and register interest in open packages. Tenders are scored 80% on price and 20% on non-financial criteria, including sustainability.
  • CurrentTransport

    Sydney Metro West

    Westmead, Sydney

    Gamuda

    Station works under way

  • CurrentTransport

    Cross River Rail

    Woolloongabba, Brisbane

    Pulse consortium

    Station fit-out and testing

Supplying this job?

Send your plans or a list. The Project ID goes with your quote, so we match it to the job.

CallGet a quote

Set your delivery site

We deliver Australia-wide. Your site goes with your quote request, and freight is quoted with your order.